RA with Method 07- POC Method on Basis of Project Progress Value

$
0
0

Hi Experts.

 

Have anyone done the RA with Method 07- POC Method on Basis of Project Progress Value

 

Have some issue while running RA.

The issue is while running the RA, System calculates the Planned Cost. in kka2 it is showing only planned material cost, it is not updating my planned secondary cost element  cost.

 

Any advice and  help will be highly appreciated

  