Hello,
I'm trying to create a Cost Center Delta Initialization load using EPM in BPC. We want to pull both the cost element 0AMOUNT (dollar values), and the 0QUANTITY (units) of activity types. Previously we would run CLEAR for actual 0MOUNNT then run LOAD_INFOPROV_UI to bring in 0AMOUNT. Then we would run CLEAR for actual 0QUANTITY, and run LOAD_INFOPROV_UI to bring in 0QUANTITY separate. We ran into the issue when trying to run the delta initialization separate that "Selection overlaps with delta initialization." When we try to run both 0AMOUNT and 0QUANTITY on the same Delta load we only pick up activity quantity, and not 0AMOUNT dollar values for cost elements.
Is there a way to run the two delta loads separately without getting the selection overlap error, or get both 0AMOUNT loaded to 0COSTELMNT, and 0QUANTITY loaded to 0ACTTYPE?
Below is the mapping from the transformation file when trying to pull both 0AMOUNT and 0QUANTITY in the delta load.
Thanks,
Lindsey
Message was edited by: Lindsey Demro