Quantcast
Channel: SCN: Message List - Software Support and Maintenance
Viewing all articles
Browse latest Browse all 2823

Multiple Holiday Calendar to Single PSA

$
0
0

Dear Experts

 

I have a requirement where 2 Employees from the same PSA are following a different calendar. Is there any way through which I can tag Employees from same PSA to different calendars. How to fix this requirement?

 

And in another case I have some sales Employees working in different states where I don't have company office (No PSA). These Employee however follow the state's calendar where they are working. How can such kind of assignment be made where EE is assigned to PSA in Delhi but he follows calendar of UP as he is working in UP.

 

Please suggest.

Regards


Viewing all articles
Browse latest Browse all 2823

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>