Dear experts:
I am dealing with the dates planning on network activities and I face a problem when the planned sequence of activities is not maintained in the actual confirmations; please let me explain it with an example:
The planned sequence is:
Act.1 --> Act. 2 --> Act. 3 (the relationships are Start-Finish)
The actual confirmations set that the Act.3 was started before Act.1 and Act.2 were finished, against planned sequence.
Therefore, we have an “out-of-sequence” scenario.
I would like to keep the confirmed part of the activity 3 duration in the actual dates and the remaining part of the duration in accordance with the precedence of Act.2; this is some kind of “split” of the activity duration (this is possible in other planning software products).
The SAP PS scheduling options allows to not taking into account de actual dates, but I could find no options to configure what I need (the “splitage” of the duration).
Could somebody advise if there is some way to configure SAP PS scheduling to manage the out-of-sequence scenario “splitting” the activities duration?
Thank you very much in advance.