Dear Support
We are getting the below error at the time of settlement of process order.
Settlement type GES: Total percentage in distribution rules <> 100%
Message no. KD562
Diagnosis
The distribution rule percentage total is 90.00 for settelement type GES.
- Settlement type FUL:
The total of the distribution rule percentages must always be 100%.
Example:
1. Receiver cost center 4711 20%
2. Receiver cost center 4712 80%
Total 100% - Settlement type PER
You can use the settlement profile to stipulate whether the periodic settlement settles 100% of the costs, or whether less is allowed.
Procedure
Maintain the settlement rule for the sender. You can maintain additional distribution rules, change the existing rules or create a different settlement profile (parameters). The settlement rule for a sender can be maintained using the appropriate master data transaction.
Settlement rule of the process order is updated with 90%. If we put manually 100% process order will settle completely. In the costing view of the material joint production has maintained as 90% to the main product and 10 to the co product. Price control is standard cost.
Screenshot of costing view joint production.
Kindly give solution for the same.