Hello,

I have a question.

 

You can change the key of the control centers work without affecting the operations that are linked in these work centers?

 

That is, if I change the control key  in the work center X, the maintenance operations that are linked in this work center.

example:

Before the change:

Work center - X - control key  - pm1

Order 1010 - Operation 10 - work center X - control key pm1

 

After the change:

Work center - X control key - ZPM1

Order 1010 - Operation 10 - work center X - control key ZPM1 - wrong!

Order 1010 - Operation 20 (new) - work center X - control key pm1 -ok

Automatically I changed the control key in the work center, this change has been replicated to the maintenance orders. Is it possible to change the control key  in the work center and keep the control key without changing the operations that were already open?

 

  thank you